Main Street project hits final stretch as downtown Mansfield braces for Final Friday crowds
The 83% complete project still targets an Oct. 31 finish, but downtown storefronts that endured detours face open questions about who pays for the renewal.
By Staff · September 29, 2026
The Main Street Improvement Project is 83% complete and still targeting an October 31 finish — but for the independent storefronts that lived through roughly 20 months of orange barrels and detoured traffic, the question of who actually pays for downtown's renewal is still open.
The roughly $20.3 million streetscape overhaul runs from 6th Street to 1st Street, plus Park Avenue from Main to Diamond. Work began in February 2025, and Downtown Mansfield Inc. issued a press release in late September saying the project is nearing the finish line. About 82% of the cost is funded by state, federal, and private grants, with the remainder coming from city funds. External grant awards include a $7.38 million Federal Highway Administration RAISE grant, $4 million in Ohio Department of Transportation Transportation Alternatives Program funds, and roughly $1.9 million each from the Richland County Regional Planning Commission and ODOT safety funds, plus state capital and strategic investment grants.
What's done, and what drivers will still notice
Much of the heavy lifting is finished: electrical wiring for traffic signals at Park Avenue and Main Street, conduit and wire along Park Avenue to Second Street, new light pole installation, removal of the old traffic signal at Sixth and Main, a pedestrian flasher near DLX, and much of the curb, sidewalk, and plaza and stone veneer work.
What remains is the part anyone behind a wheel will feel first: final resurfacing across the corridor, pavement markings, signals and wayfinding signage, the conversion of Main Street to two-way traffic, final architectural features — the north and south plazas, arches, and lighting — and landscaping.
As of late July, the remaining work was concentrated on the south end near First and Second streets. Mayor Jodie Perry, after talking with City Engineer Bob Bianchi, put the project on track for a late October 2026 completion.
The Park Avenue intersection remained closed to all traffic as of July 2026, with Main Street traffic detoured via Mulberry Street and Diamond Street and Park Avenue traffic directed to Third Street and Fourth Street. Project officials said drivers could still reach businesses near Park Avenue via Diamond Street, Main Street, North Park Street, and South Park Street, with only minor traffic delays expected in the final months.
What it cost the storefronts that stayed
Hamilton on Main, at 103 N. Main St., is owned by Nicole Hamilton. She said: "We went maybe 11 months where nobody could even drive past my business."
News 5 Cleveland reported that downtown shop owners, including Hamilton on Main, faced challenges from temporary lane closures and street shutdowns that expanded beyond the initial plans.
Those disruptions had a hard edge. Park National Bank permanently closed its downtown Mansfield branch effective Sept. 15, 2026, after structural damage was discovered in a building in the heart of the Main Street Corridor Project.
Who got made whole
The city created a $50,000 small-business grant program offering $2,500 grants to eligible downtown businesses affected by the construction. Downtown Mansfield Inc. also operates a Main Street Business Resilience Grant Program, structured as first-come, first-served, with applications accepted through October 1, 2026 or until funds are allocated.
But the city has not published a list of which businesses received the $2,500 grants, or what the resilience fund paid out — so the specific storefronts that got relief, and the amounts awarded, could not be verified.
The forward-looking money flows through bigger names. John Fernyak, president of Engwiller Properties and a longtime downtown Mansfield business owner, and Mimi Fernyak donated 14 downtown buildings to the Downtown Forward project through Engwiller Properties, and Downtown Forward and a new Mansfield hotel project received a combined $1.1 million in Ohio Historic Preservation Tax Credits. Fernyak said: "We are excited to see new life, new residents, and renewed energy in the heart of downtown."
One last crowd, then the real test
The Final Friday concert series is held at The Brickyard, an outdoor amphitheater in downtown Mansfield's Historic Carrousel District, on the last Friday of May, June, July, August, and September, from 5:30 p.m. to about 10:30 p.m.
The Sept. 25, 2026 show was the season finale, with Jody & Najee opening, Frank Boyd Jr. with the Bonafide Truth in the middle, and Austin & The Syd Experience headlining. It drew a crowd to the nearly-finished corridor under pleasant weather, according to post-event coverage. Destination Mansfield's September events round-up called it "one last outdoor concert" and the final Final Friday Concert of the popular summer series.
The Brickyard is at 24 Temple Ct., and Downtown Mansfield Inc. can be reached at 419-522-0099.
The Sept. 25 show was the last Final Friday of the season, so the next regular crowd event on the corridor will not come until the series resumes. By then, the project's October 31 target will have passed. What has not been made public is a list of which Main Street businesses received the $2,500 grants, or what the resilience fund paid out — the one accounting that would tell neighbors which of the storefronts that carried downtown through the barrels were ever made whole.